Recap of 22 July, 2009
building committee meeting.
Kent Novak, Richard
Holt, Joe Tatro, Chief Pomfret and John Humble present.
JH reported that he
had been in contact with National Grid’s scheduling dept. via customer
service on 20 July and was told that continuation of electrical service
installation would take place between 21 and 28 July.
JH reported that the
sending of a letter to George Geisser of Geisser Engineering expressing the
committee’s concerns with regard to Geisser’s billings will be sent within
the next two to three weeks.
E. Osterman had
installed a second stage regulator behind the mechanical room but evidently
determined that a leak existed in the pipe between this regulator and the
tank location.
The generator
relocation effort is pending the removal of temporary power to the trailer
by National Grid, the removal of the trailer and the return of the site
contractor with suitable lifting equipment and final site clean up.
JH reported that the
guard rail credit and the charge for the building sign light, added exit
signs, interior door signs and street number sign will appear in the next
change order, change order #12.
Alhambra will provide
a CP for flag pole lighting options suggested by JMA.
When the supplier
returns from vacation, the Chief agreed to follow up with arranging
installation of address lettering to be applied to glass of main entrance
doors. JMA recommends that reverse lettering be applied to the interior
surface of the glass, that in the case of an emergency, instructions to call
“911” or use of pull box be included in lettering.
Kent Novak reported
that the Right Connection phone system installation will continue once the
building has electrical power.
Capt. Mann had
reported via a 17 July e-mail that the last 200 lb/2hr. leak test of the FP
system that included the pipe to the pump house passed.
Chief Pomfret agreed
to research fire protection systems and fire alarm systems service providers
for service contract proposals.
Kent Novak reported
that a state inspector inspected the two gas boilers on 20 July and
indicated that the installation had passed and would send a certificate to
the attention of the Chief.
Alhambra will
investigate rain gutter issues and provide down spout strainers.
Lorenson plans to
conduct another water quality test when electrical power is available for a
substantial flow of the water.
Jor Tatro and Kent
Novak visited the site and agreed on a location for the memorial stone. Joe
Tatro indicated that he plans to install the concrete base within the next
two weeks.
The Alhambra base bid
does not provide for blinds or shades for any interior or exterior window,.
Joe Tatro offered to
spread fertilizer on the seeded areas of the site the coming weekend.
The sleeves to the
bollards are expected to arrive within the next one to two weeks.
Based on a unanimously
approved motion made by Joe Tatro and seconded by Kent Novak, it was agreed
that the Ideal Shield $1,135.00 invoice for the partial delivery of the
bollards be submitted for payment.
Based on a unanimously
approved motion made by Kent Novak and seconded by Richard Holt, CP 053R1,
$641.06 for street number lettering and additional interior signage was
accepted.
JH reported that he
had charged $127.20 worth of material to the WCFD account at Koszela’s
Lumber Yard needed for installtion of the reception area finish work.
Based on a unanimously
approved motion made by Kent Novak and seconded by Richard Holt, is was
agreed that JH should be reimbursed for the kitchen hardware, $75.21.
Based on a unanimously
approved motion made by Kent Novak and seconded by Richard Holt, JMA’s
$569.40 invoice for printing expenses associated with documents required by
the town was submitted for payment.
Joe Tatro to find a
buyer for the unused galvanized steel nosing and rebar.
Kent Novak suggested
that each committee member begin compiling their own punch list to be
discussed at future building committee meetings.
The current budget
ledger compiled by Richard Holt was reviewed by the committee members
present. The cost of the project continues to remain on budget.
The next building
committee meeting is scheduled for 4:45 p.m., 29 July, 2009 at the “ye old”
Summit Station.
For 29 July, 2009
building committee meeting
Review individual
punch lists.
Update of National
Grid electric service status.
Plan for repairing
damage caused by National Grid to ground next to pole, pavement, lettering
and apron.
Update of E. Osterman
Propane’s installation. Venting, additional regulators, etc. Status of
leak test and inspection?
The generator
relocation effort is pending the removal of temporary power to the trailer
by National Grid, the removal of the trailer and the return of the site
contractor with suitable lifting equipment and final site clean up.
Status of change order
#12 to include guard rail credit (CP 036, -$10,720), light fixture for
building sign (CP 052, +$2,887.45), added interior signs and street address
sign (CP 053R1, +$641.06), added exit signs (CP 054, +$713.00), .
Flag pole light
proposals, CP 055, $1,363.73 for low voltage LED version. CP 055A, $995.00
for standard incandescent flood light version for consideration.
Chief to follow up
with arranging installation of address lettering to be applied to glass of
main entrance doors. JMA recommends that reverse lettering be applied to
the interior surface of the glass, that in the case of an emergency,
instructions to call “911” or use of pull box be included in lettering. It
appears that a decision has already been made by others to adhere a WCFD
seal to one side of the main entrance door glazing.
Fire pump house remote
annunciator in admin office has an audible and visual alarm and also has a
set of dry contacts. Does dept. want to utilize these contacts to send a
signal elsewhere?
Status of researching
fire protection and fire alarm service contract providers?
Investigation into
excessive rain water to gutter spill-over at bottom of pediment valleys.
Have strainers for
down spouts been installed?
Status of installing
temporary plugging material in handling holes of cover of walkway manhole?
Joe Tatro.
Status of drain hole
drilling in walkway manhole by Joe Tatro?
Status of determining
well water quality and conditioning?
Status of repair of
settling cracks at door #1 and #2 of apparatus bay?
Status of domestic
washer and refrigerator replacement.
Status of washer and
dryer installation requirements in wash down room.
Status of concrete
base by Joe Tatro for memorial stone.
Status of remaining
furniture proposals, i.e., file cabinets.
CO/NO sensor
certification and on going testing plan TBD.
Update status of
finish work?
Turn out gear
storage. Opening of mobile ready rack bids is anticipated for the 5 Aug. BC
meeting.
Status of restroom
accessory installation.
Shade for interior
window of Chief’s office.
Landscaping plan and
schedule.
i.Status of applying fertilizer.
ii.Seeding of touch up areas.
Identify landscaping
equipment needs.
Status of balance of
Ideal Shield bollard order?
Plan to relocate fire
danger signage?
Plan for concrete
patio?
PlymaVent installation
plan?
Review the
installation of a non activated fire hydrant.
Watch for requested
emergency vehicle signs to be installed on Victory Highway
by RIDOT.
Update of station
street signage design, availability and cost. Determine permitting
requirements.
Is there a buyer for
the unused galvanized nosing and rebar?
Schedule member
personnel for systems training.
Follow up letter to 26
June meeting with Geisser Engineering TBD.
Review construction
progress to date and schedule to completion.
Review cost ledger.
Discuss and possibly
vote upon the above and any other project related business.