Recap of 15 July, 2009
building committee meeting.
Kent Novak, Joe Tatro,
Chief Pomfret and John Humble present.
JH reported that John
Causey of National Grid engineering inspected the site on 10 July and
determined that the provisions provided by WCFD for access to the utility
poles and installation of the electric service were satisfactory with no
further alterations needed. Chief Pomfret reported that he had been
informed informally that National Grid is requiring an additional 30’ of
gravel road. JH will contact John Causey once again for clarification.
JH reported that the
sending of a letter to George Geisser of Geisser Engineering expressing the
committee’s concerns with regard to Geisser’s billings will be sent within
the next two to three weeks.
JH reported that Joe
Capobianco, E. Osterman Propane manager, visited the site this date to
assess the needs of the propane service plumbing. He determined that the
pipe already installed at the building by Germaine Plumbing will have to be
disconnected by Germaine for the installation of a second stage regulator by
E. Osterman. Alhambra was notified.
JH reported that,
according to Rick Amaral, there will be not be a credit for the labor
involved in installing the regulator as Germaine did not carry the labor as
a line item.
The generator
relocation effort is pending the removal of temporary power to the trailer
by National Grid, the removal of the trailer and the return of the site
contractor with suitable lifting equipment and final site clean up.
The guard rail credit
will appear in the next change order, change order #12.
The flag pole was
erected on 13 July by Joe Tatro and members.
JMA has been requested
to propose a light fixture to illuminate the flag. Alhambra will follow up
with cost.
Chief agreed to follow
up with arranging installation of address lettering to be applied to glass
of main entrance doors. JMA recommends that reverse lettering be applied
to the interior surface of the glass, that in the case of an emergency,
instructions to call “911” or use of pull box be included in lettering.
Striping and lettering
of pavement has been completed.
Kent Novak reported
that the Right Connection phone system installation will continue once the
building has electrical power.
It was unknown if the
leak in the FP plumbing had been resolved.
Radio antenna has been
installed.
Alhambra will
investigate rain gutter issues and provide down spout strainers.
The report of well
water quality from Lorenson was not ready.
Kent Novak reported
that he had noticed a small crack in the concrete slab propagating from a
pier at bay #2.
Jor Tatro and Kent
Novak agreed to visit the site to establish a location for the memorial
stone. Joe Tatro agreed to construct the footing for the stone but may not
be able to address the project for another 4 weeks and asked that the
delivery of the stone be delayed.
Joe Tatro stated that
he is contemplating constructing a concrete patio at the day room exit door
area.
The recently ordered
storage cabinet and computer desk had arrived and were being stored at the
Summit Station.
Based on unanimously
approved motions made by Kent Novak and seconded by Chief Pomfret, the
purchase of 30 chairs from Bus Chairs for $1,079.23, 15 tables from Sweet
Supply for $1,323.50, 5 shelving units with 120 bins from Home Depot for
$678.20 and 10 window blinds from
www.stevesblindsandwallpaper.com for $805.60 plus shipping was approved.
Chief Pomfret
requested investigation into Alhambra providing a privacy blind for the
interior window of the Chief’s office within the base bid.
With the exception of
the refrigerator, all other appliances were on site. The refrigerator
delivered was damaged and was to be replaced. Due to an omission of
information by JH, the domestic dryer delivered was assumed to be electric
but should have been propane fired. Lee’s Appliance was requested to make
the necessary change in the order.
Based on a unanimously
approved motion made by Kent Novak and seconded by Joe Tatro, Ocean State
Top Shop invoice for $3,655 was approved for payment.
Chief Pomfret stated
that the restroom accessories had been purchased for a total of $740.
It was agreed that as
a temporary measure and once the new station is operational, that the fire
danger sign presently in use at the Summit Station will be relocated to the
new site.
JH reported that a
letter had been sent to Jacob Peabody documenting the results of a meeting
at which Jacb Peabody agreed that planting of bushes/trees around the
perimeter of the pervious parking area was not necessary due to existing
natural woodlands.
Joe Tatro offered to
spread fertilizer on the seeded areas of the site.
Chief Pomfret stated
that he has requested Capt. Mann to provide JH with Plyma Vent installation
information to be passed on to Alhambra.
The sleeves to the
bollards are expected to arrive within the next one to two weeks.
The current budget
ledger compiled by Richard Holt was reviewed by the committee members
present. The cost of the project continues to remain on budget.
The next building
committee meeting is scheduled for 4:45 p.m., 22 July, 2009 at the “ye old”
Summit Station.
For 22 July, 2009
building committee meeting
Update of National
Grid electric service schedule.
Update of E. Osterman
Propane’s installation of equipment and leak testing.
The generator
relocation effort is pending the removal of temporary power to the trailer
by National Grid, the removal of the trailer and the return of the site
contractor with suitable lifting equipment and final site clean up.
The guard rail credit
will appear in the next change order, change order #12.
Status of obtaining
cost to install a spot light for the flag?
CP 053R1, $641.06, for
9” H cast Al street number (1110) mounted on main entrance pediment plus
additional interior signs already approved per CP 053, $322.14.
Chief to follow up
with arranging installation of address lettering to be applied to glass of
main entrance doors. JMA recommends that reverse lettering be applied to
the interior surface of the glass, that in the case of an emergency,
instructions to call “911” or use of pull box be included in lettering.
Status of FP system
pressure tests.
Investigation into
excessive rain water to gutter spill-over at bottom of pediment valleys.
Have strainers for
down spouts been installed?
Status of building
sign light installation.
Status of steel plugs
for holes in cover of walkway manhole?
Can holes for drainage
be drilled into walkway manhole cover?
Status of determining
well water quality and conditioning.
Status of repair of
settling cracks at door #1 and #2 of apparatus bay.
Outcome of determining
location for the memorial stone.
Status of remaining
furniture proposals.
Incidental furniture,
waste paper baskets, shelving, etc. orders.
CO/NO sensor
certification and on going testing plan TBD.
Status of domestic
dryer change out, electric to gas.
Update status of
finish work and kitchen cabinet hardware installation.
JH reimbursement for
finish work hardware, $75.21.
Turn out gear storage.
Status of restroom
accessory installation.
Janitorial equipment
purchase status.
Shade for interior
window of Chief’s office.
Landscaping plan and
schedule.
i.Status of applying fertilizer.
ii.Seeding of touch up areas.
Identify landscaping
equipment needs.
Process Ideal Shield
bollard order invoice.
Status of balance of
bollard order, sleeves.
PlymaVent installation
plan.
Watch for requested
emergency vehicle signs to be installed on Victory Highway by RIDOT.
Update of station
street signage design, availability and cost. Determine permitting
requirements.
What does WCFD do with
five 11’ sections of unused galvanized steel nosing?
Schedule member
personnel for systems training.
Follow up letter to 26
June meeting with Geisser Engineering.
Review construction
progress to date and schedule to completion.
Review cost ledger.
Discuss and possibly
vote upon the above and any other project related business.