1. Recap of 24 June,
2009 building committee meeting.
Richard Holt,
Kent Novak, Joe Tatro and John Humble present.
An attendance
correction to be made was noted by Richard Holt for the 24 June meeting.
Kent Novak was present. Chief Pomfret was not present.
Alhambra?s May
requisition was corrected to the satisfaction of the committee and signed by
Alhambra and JMA. The corrected requisition will be submitted to treasure
Glenn Underwood.
Architect Joseph
McPhee is on vacation this week so Alhambra?s June pencil requisition will
be reviewed for payment next week.
A meeting with
Geisser Engineering to discuss concerns regarding prior billings is to be
scheduled for Friday, 26 June.
JH reported that
since the work associated with paving the access to Victory Highway was
completed without incident, Alhambra has concluded that it will not be
necessary for Northern Site Contractors to pursue obtaining a certificate of
liability insurance naming RIDOT as additionally insured.
CP 036, $10,720
credit for guard rail remained outstanding. CP 050, $4,706.47, was
submitted by Alhambra for a less sophisticated guard rail design totaling
145? in length of 2? x 10? rails and 6? x 6? posts, spaced 8? on center,
36?? bellow grade and 24? above grade that the town engineer approved at the
meeting that took place on 24 June at the planning office. Joe Tatro has
offered to provide the labor for installation if WCFD purchases the
material. He estimates the total cost to be in the order of $2,500.
Alhambra
submitted CP 051, $1,606.59, for a concrete transition between the
bituminous pavement and the pervious parking area. Joe Tatro will
investigate the possibility of placing additional rotten rock in this area
rather than pay for the concrete transition. Note: Per the drawing, the
pavement surface elevation at this interface is called out to be 511.35?.
The pervious parking surface is called out to be 511?. Reason for
difference to be determined.
Alhambra has
stated that Northern Contractors will provide a filter fabric lined trench
filled with stone along the west end of the pervious parking area at no
charge to assist in the prevention of erosion in this area.
Alhambra has yet
to verify that the plumbing sub-contractor obtained a permit that includes
propane plumbing installation.
JH reported that
Koszela Lumber provided the equipment and personnel to move the generator
from the old Summit Location to the new site on 22 June. Unfortunately,
ground conditions were such that the equipment was not adequate to locate
the generator on the concrete pad. The generator was placed in bay #5 for
safe keeping. Weather permitting, Northern Site Contractors has offered to
use their larger equipment on 29 June to place the generator.
Alhambra has yet
to provide a proposal for the building sign light fixture.
JH reported that
Lorenson had obtained samples of water from the well for mineral content
testing on 17 June. Results are expected within two weeks.
After much
discussion and evaluation of the various phone system suppliers considered,
Kent Novak made the unanimously approved motion that was seconded by Richard
Holt that the contract should be awarded to The Right Connection for $4,075.
CP 049, $4,016.01
for 34 eastern red cedars to be planted around the perimeter of the pervious
parking area was discussed with no decision made. Further discussion of
prioritizing landscaping needs is required.
It was agreed
that applying fertilizing and other treatment of grassed areas will be
postponed until the fall.
Alhambra has
estimated that the cost of covering the surface of the pervious parking area
with reclaimed asphalt is $5,100. The committee decided to wait to see if
tracking of rotten rock by foot traffic onto walkways and into the building
will be a problem once the facility is in operation.
Alhambra to
determine availability of gutter/downspout strainers.
JH reported that
Alhambra has indicated that the cost for adding ?member parking only?
lettering will be minimal.
JH reported that
Capt Mann was monitoring the pressure testing of the sprinkler system and
had noted a loss of pressure. Alhambra was notified.
JH reported that
there are four locations within the building of main entrance door buzzers;
administrative office, day room, apparatus bay and hallway outside sleeping
rooms.
JH reported that
the magnetic strike is installed but unwired in the center post of the main
entrance doors and could be activated at a later date if need be.
Based on a
unanimously approved motion made by Kent Novak and seconded by Richard Holt,
it was agreed that a 3? x 5? oak table and six chairs be purchased from
Ocean State Furniture for $799 and a glass top be purchased from Kent County
Glass for $125 for the day room.
Kent Novak
offered to shop for a stainless steel hood for the kitchen stove.
A date for
delivery of appliances will be coordinated with Alhambra.
JH offered to
obtain a price for a granite pedestal for the memorial plaque once mounted
outside the present Summit Station.
Kent Novak
reported that he had performed some initial investigation into window
treatments. No decision was made at this meeting.
Grangers will be
considered as a source for restroom accessories to be supplied and installed
by WCFD. No decision was made at this meeting.
No further
information was available regarding the railing color of the mezzanine.
No further
information was available regarding the status of correcting the bollard
order.
No further
information was available regarding the building signage lighting.
Action is pending
on obtaining steel plugs for the manhole cover located in the walkway.
The current
budget ledger was presented by Richard Holt and reviewed by the committee.
The cost of the project continues to remain on budget.
The next building
committee meeting is scheduled for 4:45 p.m., 1 July, 2009 at the ?ye old?
Summit Station.
For 1 July, 2009
building committee meeting
Update of
National Grid electric service schedule.
Review June
requisition #9.
Report of 26 June
meeting with Geisser Engineering.
Update status of
propane plumbing town permitting.
Update of E.
Osterman Propane?s installation of equipment.
Status of
generator relocation effort.
Status of guard
rail installation.
Status of flag
pole bolting template and base construction and erecting flag pole and solar
powered flag pole light availability and cost.
Status of
pavement to gravel interface backfilling.
Status of west
end gravel parking area erosion control to be provided at no charge by
Northern Site Contractors.
Schedule for
striping and lettering of pavement.
Right Connection
phone system installation schedule.
Status of FP
system pressure tests.
Establish plan to
install the station radio antenna and cable. Has bracket arrived?
Are strainers
available for down spouts?
Status of steel
plugs for holes in cover of walk way manhole?
Status of
determining well water quality and conditioning.
Discuss memorial
plaque consideration. Mounted WCFD provided bronze plaque on granite
pedestal by Comoli Granite, $1,065. WCFD installs.
Status of
remaining furniture proposals.
Incidental
furniture, waste paper baskets, shelving, etc.
Ensure plumbing
for dishwasher and ice maker is provided.
CO/NO sensor
certification and on going testing plan TBD.
Establish
appliance delivery timing. Licensed plumber must install the stove.
Status of finish
work and kitchen cabinet hardware installation.
Turn out gear
storage.
Identify
specification, source and installation of rest room accessories owned by
WCFD.
i.Toilet paper dispensers (4)
ii.Paper towel dispensers (4)
iii.Hand soap dispensers. (4)
iv.Changing tables (2)
Janitorial
equipment.
Window
treatments, i.e., shades, blinds plan.
Landscaping plan
and schedule.
i.Review CP 049, $4,016.01 for planting of 34 Eastern Red Cedar Trees
ii.Significant watering plan to be established by department.
iii.Seeding of touch up areas.
Identify
landscaping equipment needs.
Status of
building signage lighting fixture order and installation cost, CP 052,
$2,887.45.
CP for 9? H cast
Al street number (1110) mounted on main entrance pediment to be submitted by
Alhambra.
Status of
mezzanine railing paint color correction.
Status of bollard
order.
Status of kitchen
cabinet invoice.
Status of
replacement of white painted stove hood with stainless steel model.
Look out for
requested emergency vehicle signs to be installed on Victory Highway by
RIDOT.
Update of station
street signage design, availability and cost. Determine permitting
requirements.
What does WCFD do
with five 11? sections of unused galvanized steel nosing?
Review
construction progress to date and schedule to completion.
Review cost
ledger.
Discuss and
possibly vote upon the above and any other project related business.