1. Recap of 3 June, 2009 building committee meeting.
Kent Novak, Richard
Holt, Chief Pomfret, Joe Tatro and John Humble present.
At the site meeting
held this date, Alhambra’s site sub contractor agreed to reduce his price
for back up to CP 040 for gravel access to National Grid’s poles. Alhambra
to revise CP 040.
JH to discuss Geisser
monthly summery letter billing with Geisser management once testing of apron
concrete has been completed.
Joe Tatro offered to
speak with E. Osterman’s salesman, Doug Fraser to request the drafted
contract be further revised to show a 2,000 gal annual purchase rather than
3,000 gal.
CP 036, ($10,720)
credit for guard rail remains pending a meeting with town engineer to be
scheduled by JMA.
The committee awaits a
CP from Alhambra for the additional striping of the apparatus bay epoxy
floor paint.
A list of companies
that service fire alarm and suppression systems and equipment was presented
for future use by the department.
Alhambra has yet to
verify that the plumbing sub-contractor obtained a permit that includes
propane plumbing installation.
There has yet to be
received a written report by JMA containing the results of an evaluation of
the impact on roof drainage due to the changing of man holes to clean outs.
At the site meeting
held this date, Rick Amaral of Alhambra stated that there would be no cost
impact of swapping carpet/VCT in multipurpose office and multipurpose room.
Kent Novak reported on
the recent research efforts carried out for identifying suitable office, day
room, sleep room, locker room and training room furniture. Based on a
unanimous approval of a motion made by Joe Tatro and seconded by Chief
Pomfret, the desks and chairs identified for the Chief’s office and
administration office were approved for purchase at a total of $4,619.70.
WCFD to provide JMA
with extinguisher specifications.
JH reported that the
kitchen cabinet installation had commenced.
No further discussion
took place regarding window treatments.
Based on a
recommendation by Joe Tatro, it was agreed that any left over loam should
remain stock piled on the property and seeded.
It was relayed to the
committee by JH that Alhambra recommends that, due to the late seeding, a
watering discipline be established in order to improve the odds of good
grass growth.
Richard Holt agreed to
perform a pH analysis of the loam in preparation for possible treatment.
JMA has determined
that there is UL rating reciprocity between Canada and the US regarding the
desired exterior building sign light fixture manufactured in Canada. WCFD
to place order.
JH reported that
Lorenson will take water samples from the well for water quality testing.
Kent Novak and Richard
Holt agreed to continue to research the phone and PA systems supplier
proposals.
Cox Cable to be
contacted for a site survey and to determine if phone service to the
building can be established without an internal phone system installed
should an internal phone system not be installed in time for the CO.
JH reported that
Alhambra has agreed to install removable steel plugs in the openings of
concern in the walkway manhole cover.
Because of next week’s
schedule for the final concrete work on the site, Joe Tatro agreed to
deliver the flag pole bolting assembly ASAP.
Update of station
street signage design, availability and cost. Pending. Determine permitting
requirements. Pending.
The current budget
ledger was presented by Richard Holt and reviewed by the committee. The
cost of the project continues to remain on budget.
The next building
committee meeting is scheduled for 4:45 p.m., 1 June, 2009 at the “ye old”
Summit Station.
For 10 June, 2009
building committee meeting
Status of Geisser
Engineering billing investigation.
Update National Grid
service access requirements resulting in CP 040R1 reduced from $7,402.78 to
$2,684.50.
Update of Alhambra
satisfying DOT/PAP liability insurance requirements.
DOT’s Mid State office
was notified on 6/5/09 of pending paving to street. PAP permit must be on
site.
CO2 sensor
certification and on going testing plan TBD.
Update status of
propane plumbing town permitting.
Review E. Osterman
Propane’s amended contract proposal and possibly accept.
i.FOB Plainfield, CT +$0.040
ii.Term 5 yrs.
iii.Min. annual purchase 2,000
gal.
iv.Min. usage fee $570
v.Permits
vi.Regulators, etc.
vii.Tank removal $89
Review CP 045, $1,000
credit for propane regulators and installation allowance.
Review CP 036,
($10,720) credit for guard rail pending meeting with town engineer.
Phone/PA vender
proposal review. (Initial needs may be satisfied with fewer phones and/or
equipment.)
i.RI Telephone
ii.CTG
iii.Affordable Telephone
iv.PASS
Result of
investigation into Cox Cable’s land line adaptability without an internal
phone system installed.
Establish plan to
install the station radio antenna and cable.
Status of roof
drainage review by CEC due to man hole substitution by clean outs.
Are strainers
available for down spouts?
Discuss CP for adding
painted markings to epoxy apparatus bay floor.
Status of plan to
relocate generator.
Status of steel plugs
for holes in cover of walk way manhole?
Status of determining
well water quality and conditioning. (Note: Little space remains in the
mechanical room for additional equipment.)
Status of flag pole
bolting template and base construction.
Status of remaining
furniture proposals.
Establish appliance
delivery timing.
List fire extinguisher
specifications.
Status of finish work.
Identify
specification, source and installation of rest room accessories owned by
WCFD.
i.Toilet paper dispensers (4)
ii.Paper towel dispensers (4)
iii.Hand soap dispensers. (4)
iv.Changing tables (2)
Window treatments,
i.e., shades, blinds plan.
Landscaping plan and
schedule. Spreading of wetting agent and anti emergence product. Results
of pH analysis. Significant watering plan will be necessary.
Discuss plan for
unused top soil.
Status of building
signage lighting fixture order and installation cost.
Schedule to provide
two weeks notice to DOT traffic engineering of CO for installation of
emergency traffic signs.
Update of station
street signage design, availability and cost. Determine permitting
requirements.
What does WCFD do with
five 11’ sections of unused galvanized steel nosing?
Review construction
progress to date and schedule to completion.
Review cost ledger.
Discuss and possibly
vote upon the above and any other project related business.