1. Recap of 29 April, 2009 building committee meeting.
Kent Novak, Richard
Holt, Chief Pomfret, Jor Tatro and John Humble present. Joseph McPhee of J.
McPhee Architects also present.
Alhambra’s April
requisition for payment of $406,723 was reviewed. Joseph McPhee recommended
that he be given more time to evaluate the justification back-up for the
amount. On a unanimously approved motion made by Joe Tatro and seconded by
Kent Novak, it was agreed that the April requisition would be submitted for
payment contingent upon Joseph McPhee’s final recommendation.
Alhambra’s The Hanover
Insurance Company bond project status inquiry was completed ready for
mailing.
Current release of
leans by subcontractors were submitted by Alhambra.
Current prevailing
wage affidavits have yet to be submitted.
It was reported that
Rick Amaral of Alhambra stated at the site meeting held this date that the
estimated project completion date is 17 June.
Based on a unanimously
approved motion made by Kent Novak and seconded by Richard Holt, it was
agreed that Geisser Engineering’s 04/11/09 - $319.35 and 04/25/09 - $750
invoices be submitted for payment.
Based on a
recommendation made by Chief Pomfret, it was agreed that, as an additional
surface, it would be prudent to have Geisser Engineering perform concrete
testing of the apron material.
Based on a unanimously
approved motion made by Richard Holt and seconded by Kent Novak, it was
agreed that J. McPhee Architect’s 4/29/09, $2,400 invoice be submitted for
payment.
Joseph McPhee stated
that he is attempting to obtain a CAD drawing of the site plan so that he
can properly place on record alterations made to concrete walkways, apron,
etc. (It was noted at today’s site meeting that CEC will be asked to
formally review the impact of the roof drainage flow due to the change made
(CP 006/CO 002R4) from man holes to clean outs.)
The decision to paint
the fascias and gable louver trim was placed on hold pending obtaining cost.
The 12’ x 12’ patio
slab CP 032, $3,185 was rejected. Based on a unanimously approved motion
made by Chief Pomfret and seconded by Kent Novak, it was agreed that
Alhambra will proceed with constructing the originally designed 5’ x 5’
concrete pad at the day room door but would be requested to not place loam
in the area where the patio is intended to be placed in the future.
Status of power and
data drop at reception station is pending submittal of CP.
Status of two
additional phone drop considerations in apparatus bay, one next to door 126
and one next to door 130A is pending submittal of CP.
Alhambra has agreed to
reverse the multipurpose closet door swing so that it swings out of rather
than into the closet.
Status of bollard
design and credit is pending Alhambra’s review.
Joseph McPhee will
provide back-up for time sensitive bollard PO(s) to be initiated by WCFD and
Alhambra to install. Joseph McPhee to specify type N mortar pad under
bolting.
Ansul System and foam
installation submittal will be provided by Alhambra.
Status of overhead
vapor barrier possible credit pending Alhambra’s review.
Alhambra to provide a
CP for smoke seals installed on doors 128 and 129, laundry and EMT storage.
A copy of key matrix
was hand delivered to Joseph McPhee by Chief Pomfret.
Status of swapping
carpet/VCT in multipurpose office and multipurpose room pending Alhambra’s
review.
Interior paint colors
were confirmed based of a color pallet provided earlier by PRE. Color of
epoxy coating in apparatus bays yet to be confirmed.
It has been formally
established by Joseph McPhee that the galvanized steel nosing originally
intended for installation on the edge of the slab floor and between the slab
floor and asphalt paving will be omitted from the project. (Note: Since
the nosing is custom made, already fabricated and on site, there will be no
credit.)
Joe Tatro agreed to
contact E. Osterman to obtain clarification on its propane pricing. Chief
Pomfret will discuss Buckley’s proposal with Matt Buckley for further
clarification.
Kitchen cabinetry,
reception station panels and counter top purchase orders have been initiated
by WCFD.
Dimension limits for
refrigerator, dishwasher, microwave oven, gas stove, domestic washer & dryer
were provided by JH.
Since it is
anticipated that the cost of furniture will exceed $5,000 and with the
realization that WCFD’s procurement procedure requires that a call for bids
will have to be advertised, Joseph McPhee suggested that the interior
designer that designed the furniture layout be contacted with a request to
create a bid package. It was agreed that Joseph McPhee proceed with the
contact and obtain a proposal.
Landscaping. Property
line buffer needs, defined seeded areas, plantings and specialty
trees/bushes, enhancements to driveway entrance, stonework, etc. Establish
schedule for planting. Pending JMA’s input
CP 031, $2,942 for
addition of bollards at propane tank and pump house is rejected. Placement
of boulders will be included within the final landscaping plan by JMA.
Phone/PA vender visit
schedule remains for May 6.
The committee has
accepted JMA’s concept modification of the building signage, i.e. two lines
containing the letters for “Summit Station and Western Coventry Fire
District”. Cost of additional lettering to be determined. JMA to provide
back-up to WCFD for signage lighting purchase order. On a unanimously
approved motion made by Richard Holt and seconded by Kent Novak, the
committee agreed to an exterior lighting fixture costing no more than $500.
Alhamra to install for a TBD fee.
Status of DOT type
emergency vehicle street sign installation pending Alhambra’s review to
determine ownership and scope. JH to review DOT permit information.
Update of station
street signage design, availability and cost. Pending. Determine permitting
requirements. Pending.
Joe Tatro recommended
that a 24” dia. X 54” ABS pipe be installed by the contractor at the
intended location of the flag pole as a form for its base. Joe Tatro agreed
to provide the bolting template and the necessary galvanized bolts.
JMA will provide a
drawing showing required location of fire extinguishers. WCFD to provide
and install.
JMA will investigate
the necessary scope for a guard rail between pavement and the retention
pond.
It was agreed that
placement of the hot water heater outside the mechanical room and to the
left of the mechanical room door would not present a problem for the
department.
JH reported that
Lorenson had provided 600’ of 1” plastic pipe for future irrigation needs
and that pipe had been installed in existing trenches by both the site
contractor and Lorenson.
The current budget
ledger was presented by Richard Holt and reviewed by the committee. The
cost of the project continues to remain within budget.
The next building
committee meeting is scheduled for 4:45 p.m., 6 May, 2009 at the “ye old”
Summit Station.
For 6 May, 2009 building
committee meeting
Review JMA’s 4/30/09
invoice for $3,949.
Update propane vender
terms and plan.
Review CP 033,
$953.53, for power and data drop at reception station.
Review CP 034,
($7,170) credit for millwork.
Review CP 035,
$2,693.09 for increased cost of paving material above the base bid carrying
cost of $66/ton.