To:                  Western Coventry Fire District Board of Directors

Subject:           NEW FIRE STATION BUILDING COMMITTEE REPORT

Date:               November 20, 2008

 

  1. There have been five advertised building committee meetings since the October 16 report.  This brings the total number of building committee meetings to 26 since the past WCFD annual meeting in April.
  2. Geisser Engineering has been commissioned by WCFD to carry out all construction testing prescribed by code and by the structural engineer.
  3. Weekly site meetings between the G/C, superintendent, subcontractors and JH have commenced all be it that power has yet to be tied to the temporary pole at the street by National Grid therefore there is no heat or light in the trailer.
  4. Waterman Engineering is presently working with DEM/Wetlands to resolve deficiencies in the latest site design (drawing) that were sighted on Nov. 7 by DEM.  This DEM/Wetlands Determination process is causing the scope of site work that can be addressed to be seriously limited.  Much of the foundation work under the jurisdiction of the at-risk foundation permit has been completed.  Fortunately, the building official has permitted the installation of plumbing associated with the foundation prior to the issuing of a full building permit.  On Oct 8, the DEM/Wetlands supervisor informed JH that the determination process will take 30 to 40 more days.  The 40th day was Nov. 17.  There has been no indication that a DEM representative has visited the site.
  5. The septic area has been brought up to its final grade level.  The under slab grade will be established and back filling around the foundation will take place within the week. Further site work that includes the well installation and certification, cistern installation, parking area and driveway grading and retention pond installation are on hold until DEM/Wetlands has completed its determination process.
  6. Installation of the radiant heat plumbing and floor slab also romaine on hold pending DEM’s determination.
  7. Approved change proposals to the contracted amount to date total $56,007, bringing the grand total to $1,721,337.  These changes include the installation of radiant heat throughout the building, additional fill that was required to replace a greater depth of subsoil under the building footprint than anticipated and provisions for the later addition of a concrete apron if the budget allows.
  8. Preliminary indications and estimates suggest that alterations to the present site design due to the town engineer’s findings and DEM/Wetlands comments will result in an additional change proposal of $48,000.
  9. A concrete apron of appropriate size directly in front of the apparatus doors will result in an additional $11,060.  It is hoped that the funds available will allow for a concrete apron to be installed.  Asphalt pavement, as presently specified, tends to compress and/or shift under the stress of a static load such as a tanker.  
  10. A special use permit application for the pervious parking area has been filed with the town’s zoning office.  Abutters within a 200 ft. radius have been notified via a registered letter of the Dec. 3 hearing.  An attorney is required to represent WCFD at this hearing for recording purposes.  Attorney Harsch will carry out this task.    

 

 

 

 

The following is not an illusion.

 

 

 

 

 

Respectfully,

Committee: John Humble (C), Kent Novak, Richard Holt, Denis Fournier, Chief Pomfret, Joe Tatro, Glenn Underwood