To:                  Western Coventry Fire District Board of Directors

Subject:           NEW FIRE STATION BUILDING COMMITTEE REPORT

Date:               December 18, 2008

 

  1. The building committee has maintained its weekly meeting schedule.
  2. Temporary power was introduced to the site on Dec. 2.
  3. The Zoning Board approved the pervious public parking area on Dec. 3.
  4. A 300’ well was drilled on Dec. 3.  Initial yield results appear to be in the vicinity of 70 – 80 gpm.  The well will be certified by Dec. 19.
  5.  An “insignificant alteration” permit was granted by DEM/Wetlands on Dec. 10.
  6. The DOT/PAP permit has yet to be granted although informal communications between Waterman Engineering and DOT/PAP suggests that there should be no problem in acquiring the permit.
  7. With the well certified, the town engineer’s approval of the site design (pending) and having the approval of DEM/Wetlands, DEM/OWTS and DOT/PAP (pending) allows for an administrative approval of the project by the Planning Commission and application for a full building permit.
  8. As a precaution due to the upcoming potentially freezing temperatures, the contractor has decided to close the building in before installing the radiant floor heat plumbing and slab floor.
  9. The underground running of plumbing pipes and electrical conduit with the foundation perimeter is complete and inspected.
  10. The masons are on site constructing the exterior and interior block walls at this time.
  11. Approved change proposals to the construction contract amount to date total $56,428, bringing the grand total to $1,721,758.  These changes include the installation of radiant heat throughout the building, additional fill that was required to replace a greater depth of subsoil under the building footprint than anticipated and provisions for the later addition of a concrete apron if the budget allows.
  12. Preliminary indications and estimates suggest that alterations to the present site design due to the town engineer’s findings and DEM/Wetlands and DOT/PAP comments will result in an additional change proposal of $50,000.  A concrete apron of appropriate size directly in front of the apparatus doors will be considered resulting in an additional cost of $11,060.  These two additions will bring the construction total to $1,782,818.
  13. Excluding landscaping, furniture, additional fixtures and equipment if needed, the present total soft cost estimate is $227,770, leaving $189,412 of the $2.2M total budget for landscaping, FF&E and a contingency.
  14. The department officers are actively investigating the availability of used or discounted furnishing in good condition and phone/radio system venders.

 

 

 

 

Respectfully,

Committee: John Humble (C), Kent Novak, Richard Holt, Denis Fournier, Chief Pomfret, Joe Tatro, Glenn Underwood